Construction planning & status
Our construction project started in 2024 and is currently in construction phase II.
Year | Phase | Details | Status |
| 2023-25 | Preparation | Design & Construction Planning Administrative Authorisations | Completed |
| 2024 | Phase I | Property preparation & wall Access road | Completed |
| 2025-26 | Phase II | Foundation of all blocks Construction of first block | In construction |
| 2026-27 | Phase III | Construction of second block Construction of third block | Not started |
Images of the Building Site
Phase I
April 2024: Construction of the access road to the property
Phase I
June 2024: Construction of the property wall
Phase I
December 2024: Consolidation and leveling of the access road
Phase I
December 2024: Earthworks & Leveling
Phase II
August 2025: Formwork for the foundation and columns in reinforced concrete
Phase II
August/September 2025: Laying the cement mortar screed on the foundation
Phase II
August/September 2025: Shell of the first floor
Financing of the remaining construction phases
First block - already financed
Second block - amount required: €50,000
The decision on the implementation of the third block will be made at a later date.
Help us build the Future Citizen Children's Home with your construction donation!