Construction planning & status
Our construction project started in 2024 and is currently in construction phase I.

Year | Phase | Details | Status |
2023-24 | Preparation | Design & Construction Planning Administrative Authorisations | Completed |
2024 | Phase I | Property preparation & wall Access road | In Progress |
2024-25 | Phase II | Foundation of all blocks Construction of Block A | Not started |
2025-26 | Phase III | Construction of Block B Construction of Block C | Not started |
Images of the Building Site

Phase I
April 2024: Construction of the access road to the property

Phase I
June 2024: Construction of the property wall
Financing of the remaining construction phases
The required budget amounts currently to: 300.000 €
Help us to reach the required budget through a building donation!