Construction planning & status

Our construction project started in 2024 and is currently in construction phase II.


Year

Phase

Details 

Status

2023-25PreparationDesign & Construction Planning
Administrative Authorisations
Completed
2024Phase IProperty preparation  & wall
Access road
Completed
2025-26Phase IIFoundation of all blocks
Construction of first block
In construction
2026-27Phase IIIConstruction of second block
Construction of third block
Not started



Images of the Building Site 

Phase I

April 2024: Construction of the access road to the property

Phase I

June 2024: Construction of the property wall

Phase I

December 2024: Consolidation and leveling of the access road

Phase I

December 2024: Earthworks & Leveling

Phase II

August 2025: Formwork for the foundation and columns in reinforced concrete

Phase II

August/September 2025: Laying the cement mortar screed on the foundation

Phase II

August/September 2025: Shell of the first floor

Phase II

Oktober/November 2025: Shell construction of the third floor. Installation of partition walls and windows on the ground floor and first floor.

Phase II

Oktober/November 2025: Final concrete slab of the top floor. Completion of the partition walls and windows on the ground and first floors.

Phase II

January/February 2026: Completion of all external walls and inner room partition walls of all floors as well as the rooftop wall and the top floor wall

Financing of the remaining construction phases


First block - already financed

Second block - amount required: €50,000


The decision on the implementation of the third block will be made at a later date.