Construction planning & status

Our construction project started in 2024 and is currently in construction phase II.


Year

Phase

Details 

Status

2023-25PreparationDesign & Construction Planning
Administrative Authorisations
Completed
2024Phase IProperty preparation  & wall
Access road
Completed
2025-26Phase IIFoundation of all blocks
Construction of first block
In construction
2026-27Phase IIIConstruction of second block
Construction of third block
Not started



Images of the Building Site 

Phase I

April 2024: Construction of the access road to the property

Phase I

June 2024: Construction of the property wall

Phase I

December 2024: Consolidation and leveling of the access road

Phase I

December 2024: Earthworks & Leveling

Phase II

August 2025: Formwork for the foundation and columns in reinforced concrete

Phase II

August/September 2025: Laying the cement mortar screed on the foundation

Phase II

August/September 2025: Shell of the first floor

Financing of the remaining construction phases


First block - already financed

Second block - amount required: €50,000


The decision on the implementation of the third block will be made at a later date.