Construction planning & status
Year | Phase | Details | Status |
| 2023-25 | Preparation | Design & Construction Planning Administrative Authorisations | Completed |
| 2024 | Phase I | Property preparation & wall Access road | Completed |
| 2025-26 | Phase II | Foundation of all blocks Construction of first block | In construction |
| 2026-27 | Phase III | Construction of second block Construction of third block | Not started |
Images of the Building Site
Phase I
April 2024: Construction of the access road to the property
Phase I
June 2024: Construction of the property wall
Phase I
December 2024: Consolidation and leveling of the access road
Phase I
December 2024: Earthworks & Leveling
Phase II
August 2025: Formwork for the foundation and columns in reinforced concrete
Phase II
August/September 2025: Laying the cement mortar screed on the foundation
Phase II
August/September 2025: Shell of the first floor
Phase II
Oktober/November 2025: Shell construction of the third floor. Installation of partition walls and windows on the ground floor and first floor.
Phase II
Oktober/November 2025: Final concrete slab of the top floor. Completion of the partition walls and windows on the ground and first floors.
Phase II
January/February 2026: Completion of all external walls and inner room partition walls of all floors as well as the rooftop wall and the top floor wall
Financing of the remaining construction phases
First block - already financed
Second block - amount required: €50,000
The decision on the implementation of the third block will be made at a later date.